The specialized All-Union control body “Soyuzorgbumprom” completed installation of processing equipment, and the firm “Escher-Wyss” supervises the installation of equipment supplied.
On February 4th at 11:30p.m. the first cardboard is produced. On March 30, the first production complex goes into operation, producing 100 thousand tons of uncoated cardboard annually. Construction on the paper production facility begins.
On January 28th, the second production complex begins operation, also producing 100 thousand tons of uncoated cardboard and 20 thousand tons of sheet cardboard annually. The first export deliveries are shipped.
The planned production capacity of 200,000 tons per year is achieved.
On February 20 at 6:12 p.m. the first toilet paper is produced. In June, paper machine No. 1 is commissioned and the shop for processing paper in rolls begins to work.
The millionth ton of cardboard is produced, and the second tissue machine is put into operation.
The workshop of consumer goods is commissioned.